Mooring System Optimisation for Floating Production Systems

The development of the offshore industry commenced with the use of fixed structures. As development accelerated with the discovery of oil and gas in deeper waters, the use of floating structures became commonplace. The pioneering nature of the search for hydrocarbons from beneath the ocean has resulted in many innovative engineering solutions. As confidence in the successful application of engineering solutions to the development of offshore oilfields has grown, the industry has required the solution of new problems such as:
·searching for oil in ever increasing water depths,
·producing oil in areas that do not have a pipeline infrastructure for exporting the oil,
·economic oil production from small ''marginal'' fields, which have field lives of only a few years (that do not justify the expense of a permanent platform),
·production very soon after discovery (oil exploration is expensive so oil companies can be more profitable by producing oil quickly in order to improve cash flow).
All these pressures have led to an increase in the number and diversity of floating structures used for oil field development throughout the 1980's and 90's. The primary concepts considered for floating oil production are Floating Production Storage and Offloading units (FPSOs), column stabilised semi-submersibles platforms, Tension Leg Platforms (TLPs) and Spars. All the above concepts, with the exception of TLPs, use catenary line mooring.
The design of mooring systems for these floating structures is a compromise between making the system compliant enough to avoid excessive forces due to wave, wind and current induced motions, and making the system stiff enough to elude damage to the riser system due to large offset. For moderate water depths and line lengths, the compliancy is obtained by deformation of the catenary shape. With increasing water depth the static compliancy of the catenary increases at a higher rate than the water depth. On the other hand, the velocity dependent drag force increases, so the low frequency dynamic motion is being reduced with increasing water depth. This makes it difficult to find a good compromise for deep water mooring systems. The relative importance of wave frequency motion compared to mean and slowly varying motions tends to decrease with increasing water depth. Another aspect in increasing the water depth is that the anchor chain becomes a less attractive mooring element, and the lighter steel wire rope becomes more interesting.
All these considerations make it easy to understand that the optimisation of a mooring system (i.e. the determination of the most reliable and cost effective solution) is cumbersome and time consuming, and, at the same time, a task of paramount importance. Optimisation algorithms and computer programs for finding minima of complex functions have been available for three decades. Applications in different fields related to marine technology have been widely published. Typically, several variables are involved, and the design solution has to satisfy a certain number of constraints in order to ensure the functionality and safety of the structure to be optimised. Both the objective function to be minimised and the constraints to be satisfied are often complicated functions of many design variables, so that a non computerised parameter variation is an huge task. Automated optimisation procedures were not feasible earlier, which is mainly due to the complex analyses involved in evaluating the dynamic responses of both the Floating Production System (FPS) and the mooring lines. The development of fast and efficient methods for frequency-domain mooring analysis (including the most important nonlinearities), together with the availability of more and more powerful computers, is improving the situation.
For this reason, a specific computational procedure has been developed combining efficient mooring analysis methods with a state-of-the-art standard optimisation program. The optimisation process regards the mass or the cost of the material of the mooring system. At present, the cost of the installation is not included. This is due to the complexity of modelling the installation operations. On the other hand, the variations in the line geometrical characteristic (lengths and diameters) should not have a significant impact on the installation costs. As a consequence, the evaluation of such costs can be performed ''a posteriori'' on various solutions coming from the optimisation process. Hence, the objective function to be minimised is the weight or the cost of the mooring system, while the constraints to be satisfied are safety factor requirements, maximum allowable offset, angle of attack on the anchors and several others.

CONSULTA INTEGRALMENTE QUESTA TESI

La consultazione è esclusivamente in formato digitale .PDF

Acquista
Mostra/Nascondi contenuto.
3. Characteristics of the Floating Production Platform 1. General The characterisation of the Floating Production Platform (FPP) is mainly required for the analyses on the hydrodynamic behaviour of the complete system. In addition, the description of the offloading system and the definition of the hull strength are needed for the assessment of the mooring fitness for limitations relevant to operations and to loads developing at mooring-turret interface. The input data for hydrodynamic analyses are divided into three categories on the basis of relevant priority in the influence on the design procedures foreseen in the thesis. Information relevant to the other two aspects are reported at the end of this subchapter. The floating unit to be considered has been agreed with Eni-Agip and corresponds to single skin tanker with a storage capacity of 1.5 ψ 2.0 Mbbls to be converted. 2. Main Configuration Data † Length between perpendiculars (Lpp) 338 m † Beam (B) 55.4 m † Longitudinal turret position (from AP) 348 m Drawings relevant to general arrangement and hull forms are supplied primarily for the evaluation of wind loads and current loads. Hull forms, however, are mainly needed for the calculation of the hydrodynamic properties of the vessel. The above data can change only when a different vessel is assumed. Relevant modifications generally imply the updating of all the other input data. 3. Loading Data in Design Conditions For the design procedures the following data are available: Full load Ballast = Overall mass 357337 Mg 128315 Mg = Longitudinal CoG location (from AP) 175.9 m 181.2 m = Vertical CoG location (from base line) 14.86 m 14.64 m = Inertia radii (roll) 19.33 m 19.33 m (pitch) 83.55 m 83.55 m (yaw) 88.56 m 88.56 m The reported inertia radii are defined with respect to a reference system with ZSWL=0 (see Figure 6). All of the above data change when a different vessel is assumed but also when a different design condition is considered for the

CONSULTA INTEGRALMENTE QUESTA TESI

La consultazione è esclusivamente in formato digitale .PDF

Acquista
Il miglior software antiplagio

L'unico servizio antiplagio competitivo nel prezzo che garantisce l'aiuto della nostra redazione nel controllo dei risultati.
Analisi sicura e anonima al 100%!
Ottieni un Certificato Antiplagio dopo la valutazione.

Informazioni tesi

  Autore: Sebastiano Casole
  Tipo: Tesi di Dottorato
Dottorato in Dottorato di ricerca in Ingegneria Navale
Anno: 2000
Docente/Relatore: Antonio Cardo
Correlatore: FilibertoGaleazzi
Istituito da: Università degli Studi di Trieste
Dipartimento: Dipartimento di Ingegneria Navale
  Lingua: Inglese
  Num. pagine: 148

FAQ

Per consultare la tesi è necessario essere registrati e acquistare la consultazione integrale del file, al costo di 29,89€.
Il pagamento può essere effettuato tramite carta di credito/carta prepagata, PayPal, bonifico bancario.
Confermato il pagamento si potrà consultare i file esclusivamente in formato .PDF accedendo alla propria Home Personale. Si potrà quindi procedere a salvare o stampare il file.
Maggiori informazioni
Ingiustamente snobbata durante le ricerche bibliografiche, una tesi di laurea si rivela decisamente utile:
  • perché affronta un singolo argomento in modo sintetico e specifico come altri testi non fanno;
  • perché è un lavoro originale che si basa su una ricerca bibliografica accurata;
  • perché, a differenza di altri materiali che puoi reperire online, una tesi di laurea è stata verificata da un docente universitario e dalla commissione in sede d'esame. La nostra redazione inoltre controlla prima della pubblicazione la completezza dei materiali e, dal 2009, anche l'originalità della tesi attraverso il software antiplagio Compilatio.net.
  • L'utilizzo della consultazione integrale della tesi da parte dell'Utente che ne acquista il diritto è da considerarsi esclusivamente privato.
  • Nel caso in cui l’utente che consulta la tesi volesse citarne alcune parti, dovrà inserire correttamente la fonte, come si cita un qualsiasi altro testo di riferimento bibliografico.
  • L'Utente è l'unico ed esclusivo responsabile del materiale di cui acquista il diritto alla consultazione. Si impegna a non divulgare a mezzo stampa, editoria in genere, televisione, radio, Internet e/o qualsiasi altro mezzo divulgativo esistente o che venisse inventato, il contenuto della tesi che consulta o stralci della medesima. Verrà perseguito legalmente nel caso di riproduzione totale e/o parziale su qualsiasi mezzo e/o su qualsiasi supporto, nel caso di divulgazione nonché nel caso di ricavo economico derivante dallo sfruttamento del diritto acquisito.
L'obiettivo di Tesionline è quello di rendere accessibile a una platea il più possibile vasta il patrimonio di cultura e conoscenza contenuto nelle tesi.
Per raggiungerlo, è fondamentale superare la barriera rappresentata dalla lingua. Ecco perché cerchiamo persone disponibili ad effettuare la traduzione delle tesi pubblicate nel nostro sito.

Scopri come funziona »

DUBBI? Contattaci

Contatta la redazione a
[email protected]

Ci trovi su Skype (redazione_tesi)
dalle 9:00 alle 13:00

Oppure vieni a trovarci su

Parole chiave

anchoring
cfd
floating production systems
floating structures
frequency domain mooring analysis
hydrocarbons
mooring
offshore
oil & gas
optimisation

Tesi correlate


Non hai trovato quello che cercavi?


Abbiamo più di 45.000 Tesi di Laurea: cerca nel nostro database

Oppure consulta la sezione dedicata ad appunti universitari selezionati e pubblicati dalla nostra redazione

Ottimizza la tua ricerca:

  • individua con precisione le parole chiave specifiche della tua ricerca
  • elimina i termini non significativi (aggettivi, articoli, avverbi...)
  • se non hai risultati amplia la ricerca con termini via via più generici (ad esempio da "anziano oncologico" a "paziente oncologico")
  • utilizza la ricerca avanzata
  • utilizza gli operatori booleani (and, or, "")

Idee per la tesi?

Scopri le migliori tesi scelte da noi sugli argomenti recenti


Come si scrive una tesi di laurea?


A quale cattedra chiedere la tesi? Quale sarà il docente più disponibile? Quale l'argomento più interessante per me? ...e quale quello più interessante per il mondo del lavoro?

Scarica gratuitamente la nostra guida "Come si scrive una tesi di laurea" e iscriviti alla newsletter per ricevere consigli e materiale utile.


La tesi l'ho già scritta,
ora cosa ne faccio?


La tua tesi ti ha aiutato ad ottenere quel sudato titolo di studio, ma può darti molto di più: ti differenzia dai tuoi colleghi universitari, mostra i tuoi interessi ed è un lavoro di ricerca unico, che può essere utile anche ad altri.

Il nostro consiglio è di non sprecare tutto questo lavoro:

È ora di pubblicare la tesi